what is submittal

What Is a Submittal? A Complete Guide for Commercial Concrete Subcontractors

August 10, 202611 min read

Most commercial concrete subcontractors are comfortable on the estimating side of their business. The takeoff, the proposal, the bid, the award. But once the subcontract is signed and the job kicks off, a different set of requirements comes into play. And for concrete subs who haven't worked on heavily documented commercial projects before, the submittal process is often the first thing that catches them off guard.

A construction submittal is a formal document or package of documents that a subcontractor prepares and submits to the GC and design team for review and approval before specific materials, products, or methods can be used on the project. It's not paperwork for its own sake. It's the mechanism the project team uses to confirm that what you're planning to install actually matches what the drawings and specifications require.

For a commercial concrete subcontractor, submittals are part of the project support process that begins the moment the subcontract is executed and runs alongside the field work throughout the job. Getting them right, submitted on time, and tracked carefully is as important to the financial health of the job as the estimate that won it. Miss a submittal, get one rejected, or submit the wrong information, and you can find yourself unable to pour concrete while the GC's schedule keeps moving without you.

What a Submittal Actually Is and What It's Not

The word "submittal" gets used loosely in construction, so it's worth being precise about what it means in the context of a commercial concrete scope.

A submittal is documentation that proves your proposed materials, methods, or products comply with the project specifications. It's not the same as a shop drawing in the strictest sense, though shop drawings are one type of submittal. It's not a change order request. It's not an RFI. A submittal is a pre-construction approval step: you're showing the engineer of record, the architect, or the GC what you intend to use before you use it, so they can confirm it meets the design intent.

The distinction matters because submittals and contract documents work together. Your subcontract references the project specifications, and those specifications define what submittals you're required to provide and when. Reading the spec book before the job starts, not after, is what allows you to build a complete submittal list before the first pour is scheduled. Missing that step is one of the bid management process errors that quietly derails jobs that were priced and won cleanly.

Submittals vs. AIA Pay Applications: Understanding the Difference

These two terms sometimes get conflated, especially by concrete subcontractors who are new to heavily documented commercial projects. They're related in the sense that both are part of the formal project administration process, but they serve completely different purposes.

A submittal is a pre-construction or pre-installation approval document. It happens before the work, before materials are ordered or installed, and its purpose is to get the design team's sign-off that what you're proposing to use complies with the specifications. Approving a concrete mix design before the first truck arrives is a submittal. Getting the rebar shop drawings stamped before fabrication begins is a submittal.

An AIA pay application is a billing document. It's the formal mechanism by which you request payment for work already completed during a defined billing period. It references the schedule of values established at the start of the project, shows percentage of completion for each line item, and gets certified by the GC and architect before the owner releases funds.

The connection between the two is real and worth understanding: work that hasn't gone through the proper submittal approval process may not be certifiable on a pay application, even if it's been physically completed in the field. That's one of the less visible ways submittal delays can affect cash flow on a commercial concrete job. For a deeper look at how the billing side works, the AIA pay application process is worth reading alongside this article.

The Submittals a Commercial Concrete Subcontractor Typically Needs to Provide

construction submittal workflow

The specific submittals required on any project are defined by the specification sections relevant to your scope, typically Division 03 for cast-in-place concrete. But across most commercial concrete packages, the following categories appear consistently.

Concrete mix designs

This is the most fundamental submittal for a concrete subcontractor. Before any concrete is placed, the design team needs to approve the mix design your ready-mix supplier proposes to use. That approval confirms the specified compressive strength, water-to-cementitious materials ratio, aggregate size, admixtures, and any special requirements like air entrainment, fiber reinforcement, or supplementary cementitious materials. The mix design submittal typically comes from your ready-mix supplier and includes supporting strength test data, usually 28-day break results from previous batches of the same mix. On federally funded or public projects with strict material specifications, the approval timeline can stretch significantly, and submitting early is the only reliable way to protect your pour schedule.

Reinforcing steel shop drawings

On structural concrete scopes, rebar shop drawings are a required submittal on virtually every commercial project. The fabricator who supplies your rebar prepares these drawings showing bar placement, sizes, lengths, bends, lap splice locations, and any special conditions like epoxy coating or mechanical splices. Because fabrication typically takes two to four weeks after approval, submitting rebar shop drawings late is one of the fastest ways to create a schedule problem that wasn't in your estimate. This is especially critical on structural packages, where the complexity of the reinforcing steel is fundamentally different from what flatwork requires, as covered in the structural concrete vs. flatwork estimating breakdown.

Formwork submittals

On complex structural scopes, particularly shoring systems, forming systems for elevated slabs, or any temporary works that affect structural loading, the engineer may require a formwork or shoring submittal prepared by a licensed engineer. This is more common on post-tensioned decks and elevated concrete structures than on typical flatwork or foundation work, but it's worth checking the spec on every structural scope before assuming it isn't required.

Product data sheets

Any proprietary product referenced in the specifications, including curing compounds, vapor barriers, joint sealants, waterstops, concrete admixtures, and form release agents, may require a product data sheet confirming the product meets specification requirements. These are typically straightforward but can accumulate quickly on a complex concrete scope with multiple specified products across Division 03.

Concrete cylinder test results and field reports

Some specifications require that test results be submitted to the design team or GC during the project, not just kept on file. Stancon Consultants has prepared proposals for clients that include an explicit request for test cylinder results to be forwarded throughout the project, because on public and institutional work, that documentation is often a contractual requirement tied to project closeout and final payment. Having a process for collecting and forwarding that documentation systematically is part of running a professional concrete operation, not an optional add-on.

How the Submittal Review Process Works

Once you've prepared a submittal, it doesn't go directly to the engineer or architect. It goes to the GC first. The GC reviews it for completeness, confirms it covers the right specification section, and stamps it before forwarding it to the design team for technical review. That two-step process means there are two places a submittal can be returned before it's approved.

According to BuildSync's 2025 construction submittal analysis, 35% of submittals get rejected on first review, costing an average of $805 per rejection and adding two to four weeks to project timelines. For a concrete subcontractor with multiple submittals in queue during the early weeks of a project, that rejection rate has real schedule and cost implications. A rebar shop drawing that comes back for revision means the steel doesn't get fabricated until the revised drawing is resubmitted, re-reviewed by the GC, and re-reviewed by the structural engineer. That cumulative delay is time your pour can't happen.

The review timeline itself is largely outside your control. Most structural submittals take two to four weeks for design team review, and that window can stretch to four to six weeks when the engineer's workload is heavy. What is within your control is when you submit. Getting submittals in early, well before the review period becomes a schedule constraint, is one of the most straightforward protections available to a commercial concrete subcontractor who wants to control their own pour schedule.

After the design team reviews a submittal, it comes back with a status designation. Approved means proceed as submitted. Approved as noted means proceed but incorporate the reviewer's comments, which are typically minor. Revise and resubmit means the submittal doesn't meet the specification requirements and needs to be corrected. Rejected means the product or approach doesn't comply and an alternative is required.

The Submittal Log: How to Track What You Owe and When

Every concrete subcontractor managing their own submittals on a commercial project needs a submittal log. Not a mental note. Not an email folder. A documented log that tracks every required submittal, who prepared it, when it was submitted, the current review status, and when a response is expected.

The GC typically maintains a master submittal log for the project, but that log covers every trade. Your log is specific to your scope, and it's what allows you to manage your own timeline rather than waiting to hear from the GC that a submittal you thought was under review was actually returned for revision two weeks ago.

A submittal log for a commercial concrete scope should include the specification section addressed, a description of what's being submitted, the date submitted to the GC, the date forwarded to the design team, the current status, and any required action on your end. That level of tracking is basic project administration. But it's the kind of discipline that separates concrete subcontractors who control their schedule from those who are constantly reacting to delays they didn't see coming.

Stancon Consultants manages submittal preparation and tracking as part of the project support we provide to commercial concrete subcontractors. On one national retail build-out we supported from estimate through closeout, handling submittals alongside the AIA pay applications and contract review on the same project gave the client a level of documentation control that directly supported smooth billing throughout the job. That full-cycle approach, from proposal to closeout paperwork, is what effective project support for concrete subcontractors actually looks like in practice.

What Happens When a Submittal Gets Rejected

A rejected submittal isn't a crisis, but it needs to be treated as an urgent matter rather than a routine follow-up. When a concrete submittal comes back as revise and resubmit or rejected, the clock resets on the review cycle, and the schedule impact compounds with every day you don't respond.

The most common reasons concrete submittals get rejected are straightforward: the mix design doesn't meet the specified compressive strength or w/cm ratio, the rebar shop drawing doesn't match the structural engineer's details, a product data sheet is for a different product than what was specified, or required supporting documentation like strength test data or material certifications is missing.

Each of these is preventable with a thorough spec review before the submittal is prepared. When a rejection does happen, the response needs to address every comment the reviewer flagged, not just the most obvious one. Resubmit through the GC with a clear cover letter identifying what was revised, and follow up to confirm the package is in the review queue. Don't assume a resubmitted package is being reviewed unless you've confirmed it.

The risk management discipline that protects concrete subcontractors on commercial projects comes from exactly this kind of proactive documentation management. Submittals that are tracked closely and responded to quickly rarely become schedule problems. The ones that cause real damage are the ones that sit while the pour date approaches.

Submittals and Payment: The Connection Most Concrete Subs Miss

There's a direct relationship between the submittal process and the payment process that isn't always obvious until it becomes a problem. On commercial projects, the GC and owner's representative will sometimes tie payment certification to the status of your submittals. Work that hasn't been approved through the submittal process may not be certifiable for payment even if it's been physically completed in the field.

That's not a hypothetical. It's a real exposure that shows up on commercial concrete jobs where submittals are running behind the field work. A pour that went ahead before mix design approval was received, a reinforcing package that was installed before the shop drawings were stamped—these create documentation gaps that the owner's rep can use to hold up payment certification on work that was otherwise done correctly.

Managing submittals and pay applications together, as part of the same project administration workflow, is how that exposure gets closed. Understanding how AIA pay applications work in the context of submittal status gives a concrete subcontractor the full picture of why documentation management isn't separate from financial management on a commercial project. And for concrete subs who want to review what their subcontract actually says about submittal requirements before the job starts, construction contract review is the right place to begin.

Stancon Consultants helps commercial concrete subcontractors manage the documentation that keeps projects moving—from submittals and contract review to AIA pay applications and project support. If you need help keeping your paperwork as organized as your field operations, we're here to help.

construction submittal
Back to Blog

Subscribe to Our Newsletter

to Stay Ahead in the Concrete Industry

Helping commercial concrete contractors thrive through accurate estimating and strategic business consulting.